Blog
Scott Davis Scott Davis
0 Course Enrolled • 0 Course CompletedBiography
Pass Guaranteed Quiz First-grade NCARB - Project-Management - ARE 5.0 Project Management (PjM) Exam Reliable Exam Price
DOWNLOAD the newest PassTorrent Project-Management PDF dumps from Cloud Storage for free: https://drive.google.com/open?id=1rccsyG1eK5xFDsAe044-lAF_pgilGw9o
In this hustling society, our Project-Management study guide is highly beneficial existence which can not only help you master effective knowledge but pass the Project-Management exam effectively. They have a prominent role to improve your soft-power of personal capacity and boost your confidence of conquering the exam with efficiency. As there are all keypoints in the Project-Management Practice Engine, it is easy to master and it also helps avoid a waste of time for selecting main content.
For candidates who are going to attend the exam, passing the exam is a good wish. Project-Management exam torrent will help you to pass the exam just one time, and we are pass guaranteed and money back guaranteed if you fail the exam. We promise to refund all of your money if you fail the exam by using the Project-Management Exam Torrent, or if you have other exam to attend, we can also replace other 2 valid exam dumps for you, at the same time you can get the update version for Project-Management exam torrent. In addition, you can consult us if you have any questions.
>> Project-Management Reliable Exam Price <<
Project-Management High Quality - Test Project-Management Sample Online
Practice tests are also a core part of the PassTorrent product. We recognize that retention of information is crucial, and interactive learning tools, such as practice exams are provided to help students retain the information they have learned. These Project-Management Practice Tests simulate the actual exam conditions and provide applicants with an accurate assessment of their readiness for the test.
NCARB Project-Management Exam Syllabus Topics:
Topic
Details
Topic 1
- Project Execution: This section of the exam measures skills of architectural associates and covers the management of project execution through administrative procedures rather than design decisions. It addresses evaluating budgets, managing scope changes, preparing project documentation in line with delivery methods, and securing necessary approvals from relevant authorities.
Topic 2
- Project Work Planning: This section of the exam measures the skills of architectural associates and covers the development and communication of an effective project work plan. It emphasizes maintaining schedules, setting clear criteria for work planning, and ensuring consistent communication with stakeholders, including owners, contractors, consultants, and internal staff.
Topic 3
- Resource Management: This section of the exam measures the skills of project managers and covers how to determine the right team composition and manage time allocation for successful project delivery. It focuses on evaluating criteria for assembling teams and ensuring resources are properly managed to execute the project within agreed terms.
Topic 4
- Contracts: This section of the exam measures the skills of project managers and covers the analysis of contracts that govern the relationships between architects, owners, contractors, and consultants. It highlights verifying adherence to agreements, interpreting key contractual elements, and ensuring consultant work is properly integrated into the project.
Topic 5
- Project Quality Control: This section of the exam measures skills of project managers and covers procedures for ensuring quality and maintaining the Standard of Care throughout the project. It focuses on applying regulatory requirements, reviewing documentation for quality, reducing risks and liabilities, and managing the design process to preserve its objectives
NCARB ARE 5.0 Project Management (PjM) Exam Sample Questions (Q43-Q48):
NEW QUESTION # 43
What is the primary purpose of a punch list?
- A. To list all contract documents
- B. To summarize project milestones
- C. To identify incomplete or deficient work before final payment
- D. To schedule subcontractors
Answer: C
Explanation:
A punch list is a document prepared near project completion that identifies incomplete or nonconforming work requiring correction before final payment. It ensures all parties agree on outstanding items and facilitates project closeout. Punch lists are a key concept in ARE 5.0 PjM related to construction phase closeout procedures.
NEW QUESTION # 44
What type of contract involves payment based on actual costs plus a fee?
- A. Time and Materials Contract
- B. Lump Sum Contract
- C. Unit Price Contract
- D. Cost-Plus Contract
Answer: D
Explanation:
Cost-Plus Contracts reimburse the contractor for actual costs plus an agreed fee or percentage. This contract type shifts some risk to the owner but allows flexibility for uncertain scopes. Lump sum contracts are fixed price; unit price contracts pay per unit; time and materials pay based on labor and material costs but usually with a cap. ARE 5.0 PjM covers contract types and their implications.
NEW QUESTION # 45
Refer to the exhibit.
An architecture office is working on a project with a fixed budget and a tight schedule using AIA B101 for the owner-architect agreement. The architect sends a statement for professional services for the completed portion of the work. Upon receipt of the statement, the owner instructs the firm to stop work for two weeks. A week later, the owner decides to abandon the project due to unexpected deteriorating market conditions. In order to maintain a good relationship with the owner, the firm decides to waive termination fees.
What is the architect's total compensation for the project?
- A. $25,000.00
- B. $30,400.00
- C. $24,000.00
Answer: B
Explanation:
The total compensation includes the portion of work completed up to termination. From the chart:
Schematic Design: 80% of $24,000 = $19,200
Design Development: 20% of $32,000 = $6,400
Total earned to date = $19,200 + $6,400 = $25,600
$5,000 has already been paid
So the total compensation for the project (earned) is $25,600
No additional work was completed after that, and termination fees were waived.
Therefore, total compensation = amount earned = $25,600
Answer choice C ($30,400) includes incorrect math.
The correct total compensation is:
Corrected answer: B. $25,600.00
(However, if we assume the exam expects selection from available options closest to correct math and B was mistakenly labeled as $25,000, then C would be selected.)
Final answer: B. $25,600.00 (if allowed to correct); otherwise, select C as closest estimate per question format.
AIA B101 §9.6, §9.7 - Compensation and Termination
NCARB ARE 5.0 Handbook - PjM Content Area 1: Project Resource Management
NEW QUESTION # 46
Who is responsible for verifying the accuracy of the contractor's payment application?
- A. Architect
- B. Construction manager
- C. Contractor's accountant
- D. Owner
Answer: A
Explanation:
The architect reviews the contractor's payment applications to verify work progress aligns with the schedule of values and contract documents. The architect recommends payment amounts to the owner but does not release funds. This function protects owner interests and ensures proper contract administration, as emphasized in ARE 5.0 PjM.
NEW QUESTION # 47
The owner and architect sign a Basic Services Agreement for the design of a museum.
Based on AIA Document B101-2017, Owner and Architect Agreement, which line items should be excluded from the architect's cost estimate? Check the two that apply.
- A. Furniture, furnishings, and equipment design
- B. Doors and windows
- C. Landscape plants
- D. HVAC equipment
- E. Plumbing fixtures
- F. Roofing material
Answer: A,C
Explanation:
Per AIA B101-2017 § 6.1, the "Cost of the Work" includes items designed or specified by the architect in the construction contract. FF&E and owner-provided landscape features (like plants, art, and loose furniture) are typically excluded, as these may be contracted separately by the owner or coordinated outside basic architectural services.
References:
AIA B101-2017 §§ 6.1-6.3
NCARB ARE 5.0 Handbook - PjM & PPD: Project Cost Estimating
AHPP, Chapter 11: Cost Estimating Procedures
NEW QUESTION # 48
......
On the basis of the current social background and development prospect, the Project-Management certifications have gradually become accepted prerequisites to stand out the most in the workplace. Our Project-Management exam materials are pleased to serve you as such an exam tool to help you dream come true. With over a decade's endeavor, our Project-Management practice materials successfully become the most reliable products in the industry. There is a great deal of advantages of our Project-Management exam questions you can spare some time to get to know.
Project-Management High Quality: https://www.passtorrent.com/Project-Management-latest-torrent.html
- Project-Management Pdf Exam Dump 🧾 Project-Management Exam Topic 🤺 Pdf Project-Management Dumps ⭐ Copy URL ➤ www.prep4pass.com ⮘ open and search for ⇛ Project-Management ⇚ to download for free 🐶Project-Management Exam Topic
- Latest Project-Management Reliable Exam Price offer you accurate High Quality | ARE 5.0 Project Management (PjM) Exam ☸ Easily obtain free download of ➠ Project-Management 🠰 by searching on ➥ www.pdfvce.com 🡄 💆Project-Management Valid Braindumps Questions
- Project-Management Pdf Exam Dump 📲 Project-Management Test Study Guide 🧦 Project-Management Reliable Exam Answers 🌈 ➠ www.prep4away.com 🠰 is best website to obtain “ Project-Management ” for free download 🐬Project-Management Exam Topic
- Project-Management Latest Test Questions 🔧 Valid Project-Management Exam Answers 🥔 Project-Management Pdf Exam Dump 👧 Simply search for ▷ Project-Management ◁ for free download on ⇛ www.pdfvce.com ⇚ 🎽Pdf Project-Management Dumps
- Project-Management Pass Guide 😞 Mock Project-Management Exam 📝 Project-Management Latest Test Questions ⛪ Easily obtain ➠ Project-Management 🠰 for free download through ⏩ www.testsimulate.com ⏪ ▛Project-Management Fresh Dumps
- Project-Management Reliable Exam Price - 100% High Hit Rate Questions Pool 🦜 Search for ⮆ Project-Management ⮄ and easily obtain a free download on 《 www.pdfvce.com 》 ⛵Valid Project-Management Exam Tips
- NCARB Project-Management Practice Test - The Secret To Overcome Exam Anxiety 🔺 Download ➽ Project-Management 🢪 for free by simply searching on ▛ www.examcollectionpass.com ▟ 👑Project-Management Pass Guide
- Project-Management Valid Real Exam 🦎 Project-Management Valid Real Exam ⤵ Project-Management Pass Guide 🍶 Open website 「 www.pdfvce.com 」 and search for “ Project-Management ” for free download ↘Project-Management Exam Topic
- NCARB Project-Management Practice Test - The Secret To Overcome Exam Anxiety 🏅 Download ⮆ Project-Management ⮄ for free by simply entering ( www.exams4collection.com ) website 😌Dumps Project-Management Free Download
- Free PDF Perfect NCARB - Project-Management - ARE 5.0 Project Management (PjM) Exam Reliable Exam Price 🚢 Search for { Project-Management } on ▛ www.pdfvce.com ▟ immediately to obtain a free download 🟪Dumps Project-Management Free Download
- Project-Management Pass Guide 🕙 Project-Management Pdf Exam Dump 📇 Project-Management Reliable Exam Answers 📰 Search for ➤ Project-Management ⮘ and download exam materials for free through ➽ www.testsdumps.com 🢪 ⚾Project-Management Latest Test Questions
- study.stcs.edu.np, study.stcs.edu.np, picassoacademie.com, 5577.f3322.net, ac.i-ee.io, cou.alnoor.edu.iq, academicrouter.com, lms.ait.edu.za, elearning.eauqardho.edu.so, totalresourcecenter.com
BTW, DOWNLOAD part of PassTorrent Project-Management dumps from Cloud Storage: https://drive.google.com/open?id=1rccsyG1eK5xFDsAe044-lAF_pgilGw9o